Delivering on budget & ahead of time

Due to installation efficiencies and resource pooling associated with our group, we were able to offer a highly competitive packaged price, saving approximately $23,000 for the client.

Outline: July 2018, Clifford Construction approached the Hunter Construction Group (HCG) to procure precast panels for an upcoming development. Following an introduction to our services, it was apparent HCG could assist with multiple trade packages. HCG compiled individual trade quotations into a single document for precast concrete, structural steel, aluminium windows and doors, and concrete supply. The client was impressed with the ease of accessing multiple trades, through a single point of contact.

Offer: The Hunter Construction Group quotation provided the client with competitive individual pricing for each trade. However, due to installation efficiencies and resource pooling associated with our group, we were able to offer a combined price that reflected $15 000 in savings. In addition, key members of HCG worked closely with the client and project consultants to value engineer a further $8,000 in design efficiencies. The formal agreements were finalised in August 2018.

Delivery: Hunter Construction Group understood our clients’ project deadlines and associated LD’s. To assist we issued weekly programmes to ensure our client was kept up to date on the progress of all milestones, ultimately delivering the project ahead of time and on budget.

See our members at work

Find out how the members of Hunter Construction Group can assist with your project.

Contact

Hunter Construction Group
40 Glenwood Dr
Thornton NSW 2322
Ben Harragon
Project Consultant

Contact